Backend Engineer signal: topological sort + cycle detection in a service routing context. This is a ProdMatch-owned backend engineer drill, framed as a May 2026 Google Core Infra simulation, not a copied platform question.
Company context
Google · Core Infra
Freshness
May 2026
Product surface
service routing
ProdMatch interview simulation based on product-team patterns; not a claim of a real company question.
You own service routing for a Backend Engineer loop. Given services and directed dependencies between them, return a valid execution order. If a cycle exists, return an empty list and identify that the rollout is blocked.
Input
Output
Constraints
Concepts
services: 4, deps: [[0,1],[0,2],[2,3]] -> [0,1,2,3] or [0,2,1,3]